The South Oshawa Community Centre Pool Reconstruction Project continues to advance, with several key milestones achieved since our last update. We appreciate the community's continued patience and support as work moves forward.
Project Status:
Work has advanced across several areas of the project.
Fire Suppression System
Installation of the steel catwalk has been substantially completed. The fire suppression system, along with its associated mechanical and electrical components, is also substantially complete, allowing work to continue throughout the pool area.
Interior Restoration
The architectural wood slat ceiling has now been fully installed. Tile removals have been completed, polyurethane injection work beneath the pool slab has been completed, and concrete restoration and repair work is underway. Tile reinstallation has begun along the east elevation of the pool deck, and installation of the mortar bed, marking continued progress in restoring the pool area.
Next Steps:
Crews will continue concrete forming and pouring for the new drainage system while repairing underground piping and replacing pool drains throughout the facility. Tile installation will continue on the pool deck and within the east viewing gallery as reconstruction work progresses. Once construction activities are complete, the reconstructed pool will undergo testing and commissioning to ensure all building systems and pool equipment are operating safely and as intended before reopening.
We understand how important this facility is to our residents and community groups, and we appreciate your continued patience as this work progresses. Our focus remains on completing the reconstruction safely, efficiently, and to the high standard our community expects so the pool can reopen as soon as possible.
We will continue to provide updates as the project progresses.
For questions, please contact Service Oshawa at 905-436-3311. Staff will be happy to connect you with the Project Manager.
Updated July 2026